Copying a Timeline
You want to copy a timeline from one planning activity and paste it into another planning activity.
-
Starting from the sidebar navigation, click > Planner > Calendar and navigate to the line of the element whose timeline you want to copy.
-
Right-click on the timeline which you would like to copy.
-
Choose Copy.
-
In the calendar, right click on the row of the planning activity where you would like to paste the timeline.
-
Click
.
This will display the context menu for timelines.
The timeline has now been copied.
Note: The corresponding period of the planning activity may not be occupied by other timelines.
The timeline is pasted into the row of the planning activity. The timeline has the same start and end date and is allocated to the same category. Content added with Content Enrichment is also copied.